CAPM · Question #202

CAPM Question #202: Real Exam Question with Answer & Explanation

The correct answer is B: Procurement strategy. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Once the make-or-buy analysis is completed, which document defines the project delivery method?

Options

  • AProcurement statement of work (SOW)
  • BProcurement strategy
  • CTerms of reference
  • DChange request

Topics

#Procurement Management#Procurement Strategy#Make-or-Buy Analysis#Project Delivery Method

Community Discussion

No community discussion yet for this question.