Once the make-or-buy analysis is completed, which document defines the project delivery method?
Options
- AProcurement statement of work (SOW)
- BProcurement strategy
- CTerms of reference
- DChange request
Topics
#Procurement Management#Procurement Strategy#Make-or-Buy Analysis#Project Delivery Method