nerdexam
PMIPMI

CAPM · Question #203

CAPM Question #203: Real Exam Question with Answer & Explanation

The correct answer is B: Stakeholder satisfaction should be identified immediately and managed as a project objective.. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholder, is correct?

Options

  • AThe project manager should identify and deal with stakeholders only during the execution phase.
  • BStakeholder satisfaction should be identified immediately and managed as a project objective.
  • CThe project manager should focus on project objectives and deal with stakeholders as a secondary priority.
  • DStakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.

Topics

#Stakeholder Management#Project Objectives#Stakeholder Engagement#Project Planning

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions