Question
A project team of telecommuters located in three different time zones regularly misses project deadlines. Daily meetings often start and end with the same person talking and the rest of the team listening. The project manager determines that communication among team members must be addressed. What communication step is missing from the daily meetings?
Options
- AInterpersonal communication
- BFeedback/response communication
- CPush communication
- DPull communication
Topics
#Communication management#Team communication#Meeting effectiveness#Feedback loops