CAPM · Question #197

CAPM Question #197: Real Exam Question with Answer & Explanation

The correct answer is B: Feedback/response communication. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project team of telecommuters located in three different time zones regularly misses project deadlines. Daily meetings often start and end with the same person talking and the rest of the team listening. The project manager determines that communication among team members must be addressed. What communication step is missing from the daily meetings?

Options

  • AInterpersonal communication
  • BFeedback/response communication
  • CPush communication
  • DPull communication

Topics

#Communication management#Team communication#Meeting effectiveness#Feedback loops