CAPM · Question #185

CAPM Question #185: Real Exam Question with Answer & Explanation

The correct answer is B: To monitor and record the results of executed quality management activities. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What is the purpose of the Manage Quality process?

Options

  • ATo translate the quality management plan into executable quality activities
  • BTo monitor and record the results of executed quality management activities
  • CTo determine if project activities comply with organizational and project policies
  • DTo identify project deliverables and quality requirements and/or standards

Topics

#Quality Management#Manage Quality Process#Process Monitoring#PMBOK Processes