The correct answer is B: To monitor and record the results of executed quality management activities. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What is the purpose of the Manage Quality process?
Options
- ATo translate the quality management plan into executable quality activities
- BTo monitor and record the results of executed quality management activities
- CTo determine if project activities comply with organizational and project policies
- DTo identify project deliverables and quality requirements and/or standards
Topics
#Quality Management#Manage Quality Process#Process Monitoring#PMBOK Processes