CAPM · Question #185
What is the purpose of the Manage Quality process?
The correct answer is B. To monitor and record the results of executed quality management activities. Note: Per PMBOK 6th Edition, Answer A ('translate the quality management plan into executable quality activities') is the standard definition of Manage Quality, while Answer B ('monitor and record results') typically describes Control Quality. This question as written appears to
Question
Options
- ATo translate the quality management plan into executable quality activities
- BTo monitor and record the results of executed quality management activities
- CTo determine if project activities comply with organizational and project policies
- DTo identify project deliverables and quality requirements and/or standards
How the community answered
(39 responses)- A3% (1)
- B95% (37)
- C3% (1)
Explanation
Note: Per PMBOK 6th Edition, Answer A ('translate the quality management plan into executable quality activities') is the standard definition of Manage Quality, while Answer B ('monitor and record results') typically describes Control Quality. This question as written appears to have an error in the marked answer. For exam purposes, understanding the distinction is critical: Plan Quality Management (D) identifies quality requirements and standards; Manage Quality (A per PMBOK 6) converts the quality plan into executable activities and conducts quality audits; Control Quality (B per PMBOK 6) monitors and records the results of quality activities to assess performance. If this question's source uses a different framework or edition, B may reflect an alternate definition of Manage Quality in that context.