CAPM · Question #184
For a 10-day project, activity B's duration is three days, and activity C's duration is two days. What is the duration of activity A if activities B and C are performed in parallel?
The correct answer is C. 7 days. When activities are performed in parallel (simultaneously), their combined elapsed duration equals only the longest of the two, not their sum. Activities B (3 days) and C (2 days) running in parallel take 3 days total (the longer of the two). Since the total project duration is 1
Question
Options
- A3 days
- B5 days
- C7 days
- D10 days
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C84% (26)
- D10% (3)
Explanation
When activities are performed in parallel (simultaneously), their combined elapsed duration equals only the longest of the two, not their sum. Activities B (3 days) and C (2 days) running in parallel take 3 days total (the longer of the two). Since the total project duration is 10 days, Activity A must account for the remaining time: 10 − 3 = 7 days. If B and C were sequential, they would take 5 days combined, leaving only 5 days for A. The parallel execution is the key constraint that drives the answer to 7 days.
Topics
Community Discussion
No community discussion yet for this question.