PMIPMI
CAPM · Question #184
CAPM Question #184: Real Exam Question with Answer & Explanation
The correct answer is C: 7 days. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
For a 10-day project, activity B's duration is three days, and activity C's duration is two days. What is the duration of activity A if activities B and C are performed in parallel?
Options
- A3 days
- B5 days
- C7 days
- D10 days
Topics
#Activity Duration#Parallel Activities#Schedule Calculation#Project Duration
Community Discussion
No community discussion yet for this question.