nerdexam
PMIPMI

CAPM · Question #184

CAPM Question #184: Real Exam Question with Answer & Explanation

The correct answer is C: 7 days. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

For a 10-day project, activity B's duration is three days, and activity C's duration is two days. What is the duration of activity A if activities B and C are performed in parallel?

Options

  • A3 days
  • B5 days
  • C7 days
  • D10 days

Topics

#Activity Duration#Parallel Activities#Schedule Calculation#Project Duration

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions