CAPM · Question #166
A project manager is addressing risks and potential concerns related to stakeholder management, and is clarifying and resolving previously identified issues. In which process is the project manager en
The correct answer is C. Manage Stakeholder Engagement. Manage Stakeholder Engagement is the process where the project manager actively works with stakeholders to meet their needs, address concerns, and resolve issues. Key activities include fostering engagement, clarifying ambiguities, and resolving issues that have already been iden
Question
Options
- AIdentify Stakeholders
- BPlan Stakeholder Engagement
- CManage Stakeholder Engagement
- DMonitor Stakeholder Engagement
How the community answered
(39 responses)- A13% (5)
- B5% (2)
- C79% (31)
- D3% (1)
Explanation
Manage Stakeholder Engagement is the process where the project manager actively works with stakeholders to meet their needs, address concerns, and resolve issues. Key activities include fostering engagement, clarifying ambiguities, and resolving issues that have already been identified. Identify Stakeholders (A) is about determining who the stakeholders are. Plan Stakeholder Engagement (B) is about developing strategies for engagement. Monitor Stakeholder Engagement (D) is about tracking and adjusting engagement strategies, not actively resolving issues.
Topics
Community Discussion
No community discussion yet for this question.