CAPM · Question #167

Deciding the phases of project life cycle would be considered a part of which of these knowledge areas?

The correct answer is D. Project Integration Management. Project Integration Management is the correct knowledge area. Defining the project life cycle phases is part of developing the project management plan, which falls under Integration Management. This knowledge area oversees how all project processes are coordinated and unified, in

Project Management Fundamentals and Core Concepts

Question

Deciding the phases of project life cycle would be considered a part of which of these knowledge areas?

Options

  • AProject Schedule Management
  • BProject Scope Management
  • CProject Resource Management
  • DProject Integration Management

How the community answered

(45 responses)
  • A
    9% (4)
  • B
    4% (2)
  • C
    16% (7)
  • D
    71% (32)

Explanation

Project Integration Management is the correct knowledge area. Defining the project life cycle phases is part of developing the project management plan, which falls under Integration Management. This knowledge area oversees how all project processes are coordinated and unified, including how the project is structured into phases. Schedule Management (A) manages the timeline within an established structure. Scope Management (B) defines what work is included. Resource Management (C) focuses on people and physical resources. Integration Management is the unifying knowledge area that determines how the overall project will be run.

Topics

#Project Integration Management#Project Life Cycle#Develop Project Management Plan#Project Setup