nerdexam
PMI

CAPM · Question #162

During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was

The correct answer is A. Change request. A Change Request is the correct answer. When a defect is discovered during execution, the project manager must formally document the need for repair through a change request - specifically a 'defect repair' type of change request. This is processed through Integrated Change Contr

Predictive, Plan-Based Methodologies

Question

During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Options

  • AChange request
  • BRisk response
  • CRisk management plan
  • DLessons learned

How the community answered

(21 responses)
  • A
    71% (15)
  • B
    10% (2)
  • C
    5% (1)
  • D
    14% (3)

Explanation

A Change Request is the correct answer. When a defect is discovered during execution, the project manager must formally document the need for repair through a change request - specifically a 'defect repair' type of change request. This is processed through Integrated Change Control before corrective work begins. Risk response (B) deals with proactive or reactive handling of identified risks, not discovered defects. Risk management plan (C) is a planning document, not a process action. Lessons learned (D) is a knowledge management activity, not a corrective action mechanism.

Topics

#Change Request Process#Defect Resolution#Integrated Change Control#Project Execution Phase

Community Discussion

No community discussion yet for this question.

Full CAPM Practice