nerdexam
PMIPMI

CAPM · Question #162

CAPM Question #162: Real Exam Question with Answer & Explanation

The correct answer is A: Change request. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Options

  • AChange request
  • BRisk response
  • CRisk management plan
  • DLessons learned

Topics

#Change Request Process#Defect Resolution#Integrated Change Control#Project Execution Phase

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions