PMIPMI
CAPM · Question #162
CAPM Question #162: Real Exam Question with Answer & Explanation
The correct answer is A: Change request. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?
Options
- AChange request
- BRisk response
- CRisk management plan
- DLessons learned
Topics
#Change Request Process#Defect Resolution#Integrated Change Control#Project Execution Phase
Community Discussion
No community discussion yet for this question.