The correct answer is B: Project charter and business documents. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following sets are inputs to the Collect Requirements process?
Options
- AProject charter and requirements documentation
- BProject charter and business documents
- CProject charter and stakeholder requirements
- DBusiness documents and requirements traceability matrix
Topics
#Collect Requirements process#PMBOK inputs#Project Charter#Business Documents
Community Discussion