nerdexam
PMI

CAPM · Question #161

Which of the following sets are inputs to the Collect Requirements process?

The correct answer is B. Project charter and business documents. According to the PMBOK Guide, the inputs to the Collect Requirements process include the project charter, business documents (such as the business case and benefits management plan), project management plan components, project documents, agreements, enterprise environmental facto

Predictive, Plan-Based Methodologies

Question

Which of the following sets are inputs to the Collect Requirements process?

Options

  • AProject charter and requirements documentation
  • BProject charter and business documents
  • CProject charter and stakeholder requirements
  • DBusiness documents and requirements traceability matrix

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    88% (43)
  • C
    4% (2)
  • D
    6% (3)

Explanation

According to the PMBOK Guide, the inputs to the Collect Requirements process include the project charter, business documents (such as the business case and benefits management plan), project management plan components, project documents, agreements, enterprise environmental factors, and organizational process assets. The project charter provides high-level project requirements, while business documents provide context and justification. 'Requirements documentation' (A) is an OUTPUT of this process, not an input. 'Stakeholder requirements' (C) is not a formal input category. The 'requirements traceability matrix' (D) is also an output, not an input.

Topics

#Collect Requirements process#PMBOK inputs#Project Charter#Business Documents

Community Discussion

No community discussion yet for this question.

Full CAPM Practice