PMIPMI
CAPM · Question #14
CAPM Question #14: Real Exam Question with Answer & Explanation
The correct answer is A: Develop Project Charter and Close Project or Phase. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which are examples of processes that may be used once or at predefined points in the project life cycle?
Options
- ADevelop Project Charter and Close Project or Phase
- BDefine Activities and Acquire Resources
- CControl Schedule and Conduct Procurements
- DMonitor Communications and Control Costs
Topics
#Project Processes#Project Lifecycle#PMI Process Groups#Initiating and Closing Processes
Community Discussion
No community discussion yet for this question.