CAPM Question #124: Real Exam Question with Answer & Explanation

The correct answer is C: Combining the results in all other knowledge areas and overseeing the project as a whole. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What is the project manager's responsibility in Project Integration Management?

Options

  • AEnsuring that requirements-related work is clarified in the project management plan
  • BInvesting sufficient effort in acquiring, managing, motivating, and empowering the project team
  • CCombining the results in all other knowledge areas and overseeing the project as a whole
  • DDeveloping a strategy to ensure effective stakeholder communication

Topics

#Project Integration Management#Project Manager Role#PMBOK Knowledge Areas#Holistic Project Management