CAPM · Question #124
What is the project manager's responsibility in Project Integration Management?
The correct answer is C. Combining the results in all other knowledge areas and overseeing the project as a whole. Project Integration Management is focused on unifying and coordinating all project management processes and knowledge areas to oversee the project as a cohesive whole.
Question
Exhibit
Options
- AEnsuring that requirements-related work is clarified in the project management plan
- BInvesting sufficient effort in acquiring, managing, motivating, and empowering the project team
- CCombining the results in all other knowledge areas and overseeing the project as a whole
- DDeveloping a strategy to ensure effective stakeholder communication
How the community answered
(18 responses)- B6% (1)
- C94% (17)
Why each option
Project Integration Management is focused on unifying and coordinating all project management processes and knowledge areas to oversee the project as a cohesive whole.
Clarifying requirements in the project management plan is a responsibility tied to Scope Management, not Integration Management.
Acquiring, managing, motivating, and empowering the project team describes the role of the project manager in Resource Management.
The core responsibility of the project manager in Integration Management is to combine outputs from all other knowledge areas - scope, schedule, cost, quality, risk, etc. - and oversee the entire project holistically. This ensures that all components work together toward project objectives rather than in isolation.
Developing a strategy for effective stakeholder communication is the primary responsibility associated with Communications Management and Stakeholder Management.
Concept tested: Project Integration Management - project manager role