CAPM · Question #124
CAPM Question #124: Real Exam Question with Answer & Explanation
The correct answer is C: Combining the results in all other knowledge areas and overseeing the project as a whole. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What is the project manager's responsibility in Project Integration Management?
Options
- AEnsuring that requirements-related work is clarified in the project management plan
- BInvesting sufficient effort in acquiring, managing, motivating, and empowering the project team
- CCombining the results in all other knowledge areas and overseeing the project as a whole
- DDeveloping a strategy to ensure effective stakeholder communication
Topics
#Project Integration Management#Project Manager Role#PMBOK Knowledge Areas#Holistic Project Management