PMIPMI
CAPM · Question #115
CAPM Question #115: Real Exam Question with Answer & Explanation
The correct answer is D: Reserve analysis. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?
Options
- AWhat-if scenario analysis
- BSimulation
- CAlternatives analysis
- DReserve analysis
Topics
#Contingency reserves#Reserve analysis#Cost estimation#Risk management
Community Discussion
No community discussion yet for this question.