nerdexam
PMIPMI

CAPM · Question #115

CAPM Question #115: Real Exam Question with Answer & Explanation

The correct answer is D: Reserve analysis. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

Options

  • AWhat-if scenario analysis
  • BSimulation
  • CAlternatives analysis
  • DReserve analysis

Topics

#Contingency reserves#Reserve analysis#Cost estimation#Risk management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions