CAPM · Question #115
A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?
The correct answer is D. Reserve analysis. Reserve analysis is the technique used to determine contingency reserves by assessing potential risks and uncertainties in cost or schedule estimates.
Question
Options
- AWhat-if scenario analysis
- BSimulation
- CAlternatives analysis
- DReserve analysis
How the community answered
(40 responses)- A3% (1)
- C5% (2)
- D93% (37)
Why each option
Reserve analysis is the technique used to determine contingency reserves by assessing potential risks and uncertainties in cost or schedule estimates.
What-if scenario analysis evaluates the effect of various scenarios on the project schedule, primarily used in schedule development rather than contingency determination.
Simulation, such as Monte Carlo analysis, models the combined effects of individual risks on overall project outcomes, but it is a specific analytical tool rather than the overarching technique for setting reserves.
Alternatives analysis is used to evaluate different options for meeting project requirements or resolving issues, not to determine reserve amounts.
Reserve analysis is specifically used to establish contingency reserves - amounts added to cost or schedule estimates to account for identified risks and general uncertainty. The project manager evaluates the risk exposure of the project to determine how much buffer is needed beyond the base estimate. This technique distinguishes between contingency reserves (for known-unknown risks) and management reserves (for unknown-unknown risks).
Concept tested: Reserve analysis for contingency determination
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.