CAPM · Question #114
Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?
The correct answer is A. Develop Schedule. The Develop Schedule process integrates activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
Question
Exhibit
Options
- ADevelop Schedule
- BControl Schedule
- CEstimate Activity Durations
- DDefine Activities
How the community answered
(31 responses)- A94% (29)
- C3% (1)
- D3% (1)
Why each option
The Develop Schedule process integrates activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring. It produces the project schedule, schedule baseline, and schedule data by applying techniques such as critical path method and resource optimization. This process is the point where all scheduling inputs are combined into an actionable, approved baseline.
Control Schedule involves monitoring the status of the project schedule and managing changes to it, which occurs after the schedule has already been developed.
Estimate Activity Durations focuses only on approximating the number of work periods required to complete individual activities, not the full integration of sequences and constraints.
Define Activities identifies and documents the specific actions needed to produce project deliverables but does not analyze sequences, durations, or constraints.
Concept tested: Purpose and scope of the Develop Schedule process
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.
