CAPM · Question #114

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

The correct answer is A. Develop Schedule. The Develop Schedule process integrates activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.

Predictive, Plan-Based Methodologies

Question

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

Exhibit

CAPM question #114 exhibit

Options

  • ADevelop Schedule
  • BControl Schedule
  • CEstimate Activity Durations
  • DDefine Activities

How the community answered

(31 responses)
  • A
    94% (29)
  • C
    3% (1)
  • D
    3% (1)

Why each option

The Develop Schedule process integrates activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.

ADevelop ScheduleCorrect

Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring. It produces the project schedule, schedule baseline, and schedule data by applying techniques such as critical path method and resource optimization. This process is the point where all scheduling inputs are combined into an actionable, approved baseline.

BControl Schedule

Control Schedule involves monitoring the status of the project schedule and managing changes to it, which occurs after the schedule has already been developed.

CEstimate Activity Durations

Estimate Activity Durations focuses only on approximating the number of work periods required to complete individual activities, not the full integration of sequences and constraints.

DDefine Activities

Define Activities identifies and documents the specific actions needed to produce project deliverables but does not analyze sequences, durations, or constraints.

Concept tested: Purpose and scope of the Develop Schedule process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Develop Schedule#Schedule Management#PMBOK Processes#Project Scheduling