PMIPMI
CAPM · Question #112
CAPM Question #112: Real Exam Question with Answer & Explanation
The correct answer is D: Project management plan. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following is used as an input to prepare a cost management plan?
Options
- AExpert judgment
- BLessons learned
- CCost estimates
- DProject management plan
Topics
#Cost Management#Project Planning#Process Inputs#Project Management Plan
Community Discussion
No community discussion yet for this question.