nerdexam
PMIPMI

CAPM · Question #111

CAPM Question #111: Real Exam Question with Answer & Explanation

The correct answer is C: Finish-to-Start (FS). See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?

Options

  • AFinish-to-Finish (FF)
  • BStart-to-Finish (SF)
  • CFinish-to-Start (FS)
  • DStart-to-Start (SS)

Topics

#Project scheduling#Task dependencies#Activity relationships

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions