CAPM · Question #111

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relatio

The correct answer is C. Finish-to-Start (FS). The painting task cannot begin until the mason finishes plastering, which is the classic definition of a Finish-to-Start dependency between two activities.

Predictive, Plan-Based Methodologies

Question

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?

Options

  • AFinish-to-Finish (FF)
  • BStart-to-Finish (SF)
  • CFinish-to-Start (FS)
  • DStart-to-Start (SS)

How the community answered

(33 responses)
  • A
    3% (1)
  • C
    94% (31)
  • D
    3% (1)

Why each option

The painting task cannot begin until the mason finishes plastering, which is the classic definition of a Finish-to-Start dependency between two activities.

AFinish-to-Finish (FF)

Finish-to-Finish (FF) means both tasks must complete at the same time, which does not describe a scenario where one task is blocked from starting.

BStart-to-Finish (SF)

Start-to-Finish (SF) is a rare dependency where the successor must finish before the predecessor can start, which is the inverse of the described situation.

CFinish-to-Start (FS)Correct

Finish-to-Start (FS) is the most common logical dependency, where the predecessor activity must fully complete before the successor activity can begin. In this case, the masonry plastering is the predecessor and painting is the successor - painting is blocked until plastering finishes. This is the standard sequencing relationship used when one task is a direct prerequisite for the next.

DStart-to-Start (SS)

Start-to-Start (SS) means both tasks can begin simultaneously once the predecessor starts, which contradicts the scenario where painting cannot begin at all.

Concept tested: Logical task dependency relationship types in scheduling

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project scheduling#Task dependencies#Activity relationships