CAPM · Question #111
CAPM Question #111: Real Exam Question with Answer & Explanation
The correct answer is C: Finish-to-Start (FS). See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?
Options
- AFinish-to-Finish (FF)
- BStart-to-Finish (SF)
- CFinish-to-Start (FS)
- DStart-to-Start (SS)
Topics
#Project scheduling#Task dependencies#Activity relationships