C_TS412_2021 · Question #49
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled. Which set of dates can be used…
The correct answer is A. Planned dates E. Forecast dates. In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are: Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your…
Question
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled. Which set of dates can be used for scheduled for network? Note: there are 2 correct answer for this question.
Options
- APlanned dates
- BFundamental dates
- CBasic dates
- DBaseline dates
- EForecast dates
How the community answered
(52 responses)- A94% (49)
- B2% (1)
- D4% (2)
Explanation
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are: Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates. Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work.