C_TS412_2021 · Question #50
Your customer wants to plans and post revenues for WBS elements. What is crucial for the implementation of revenues planning and posting for WBS elements?.
The correct answer is D. A sales order item has to be assigned to each WBS element used for revenue planning. Revenue planning and posting for WBS elements is a function that allows you to plan and record revenues for customer projects. The crucial prerequisite for this function is that a sales order item has to be assigned to each WBS element used for revenue planning. The sales order…
Question
Your customer wants to plans and post revenues for WBS elements. What is crucial for the implementation of revenues planning and posting for WBS elements?.
Options
- AAt least one WBS element must be a billing element.
- BThe indicator "Project type" must be set to "Customer project".
- CRevenue planning and billing must be activated in the corresponding network type.
- DA sales order item has to be assigned to each WBS element used for revenue planning.
How the community answered
(37 responses)- A5% (2)
- B3% (1)
- C8% (3)
- D84% (31)
Explanation
Revenue planning and posting for WBS elements is a function that allows you to plan and record revenues for customer projects. The crucial prerequisite for this function is that a sales order item has to be assigned to each WBS element used for revenue planning. The sales order item serves as a reference object for revenue recognition and billing. You can assign a sales order item to a WBS element in the Billing Plan tab of the WBS element master data.
Topics
Community Discussion
No community discussion yet for this question.