A business analyst (BA) at Cloud Kicks has been tasked with preparing for requirements gathering workshops for an upcoming Sales Cloud implementation. Which documentation is mast beneficial for the…
The correct answer is C. Suppliers. Inputs, Process, Outputs, Customers (SIPOC) Map. A SIPOC (Suppliers, Inputs, Process, Outputs, Customers) map is a high-level process overview tool ideal for defining project scope before detailed requirements are gathered. It identifies who is involved, what enters and exits the process, and who receives the outputs - giving…
Question
A business analyst (BA) at Cloud Kicks has been tasked with preparing for requirements gathering workshops for an upcoming Sales Cloud implementation. Which documentation is mast beneficial for the BA to define the scope of the project?
Options
- ADetailed Process Map
- BValue Stream Map
- CSuppliers. Inputs, Process, Outputs, Customers (SIPOC) Map
How the community answered
(37 responses)- A5% (2)
- B11% (4)
- C84% (31)
Explanation
A SIPOC (Suppliers, Inputs, Process, Outputs, Customers) map is a high-level process overview tool ideal for defining project scope before detailed requirements are gathered. It identifies who is involved, what enters and exits the process, and who receives the outputs - giving all stakeholders a shared understanding of boundaries. A Detailed Process Map (A) is too granular for initial scoping and is created after scope is established. A Value Stream Map (B) is used to identify waste and inefficiency in existing processes, not to define scope.