Which option is the recommended scope for a work package?

The correct answer is C. one major business capability. Option C is correct because a work package should be scoped to one major business capability, giving it a clear, manageable boundary that ties directly to a single deliverable outcome without becoming too broad or too granular to govern effectively. A (three business…

Creating and Presenting Comprehensive Business Cases

Question

Which option is the recommended scope for a work package?

Options

  • Athree business capabilities
  • Bone technical subsystem
  • Cone major business capability
  • Dno recommended size

How the community answered

(23 responses)
  • A
    4% (1)
  • C
    91% (21)
  • D
    4% (1)

Explanation

Option C is correct because a work package should be scoped to one major business capability, giving it a clear, manageable boundary that ties directly to a single deliverable outcome without becoming too broad or too granular to govern effectively.

  • A (three business capabilities) is wrong because spanning multiple capabilities increases complexity, creates cross-team dependencies, and makes it harder to track completion or assign ownership.
  • B (one technical subsystem) is wrong because work packages are defined around business outcomes, not technical architecture - framing them around subsystems confuses delivery scope with solution design.
  • D (no recommended size) is wrong because the framework does provide sizing guidance; leaving scope undefined leads to inconsistent planning and governance.

Memory tip: Think of a work package as a "one job, one capability" rule - just as a microservice ideally does one thing, a work package targets one major business capability to stay focused and accountable.

Topics

#work package scope#business capability#scope management#project breakdown