Which statement about implementation timelines is true?

The correct answer is C. The timing should be realistic, given the scope, budget, risk, and potential benefits. Option C is correct because effective implementation timelines must account for multiple real-world constraints - scope defines what needs to be done, budget limits resources, risk introduces uncertainty, and potential benefits must justify the investment. A realistic timeline…

Creating and Presenting Comprehensive Business Cases

Question

Which statement about implementation timelines is true?

Options

  • AThey should allow for the shortest total project elapsed time, regardless of risk.
  • BThey should have a good balance across a variety of business groups.
  • CThe timing should be realistic, given the scope, budget, risk, and potential benefits.
  • DThe duration should be set by a single executive sponsor so that accountability is easiest to

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    4% (1)
  • C
    73% (19)
  • D
    8% (2)

Explanation

Option C is correct because effective implementation timelines must account for multiple real-world constraints - scope defines what needs to be done, budget limits resources, risk introduces uncertainty, and potential benefits must justify the investment. A realistic timeline balances all these factors rather than optimizing for just one.

Why the distractors fail:

  • A is wrong because ignoring risk leads to unrealistic plans that collapse under pressure; risk is a critical input to timeline planning.
  • B is a red herring - balancing across business groups is a stakeholder consideration, not a principle of timeline setting.
  • D is wrong because accountability through a single executive sounds tidy, but timeline duration should be driven by technical and business reality, not a single person's decree; it also invites unrealistic top-down mandates.

Memory tip: Think of "C" as standing for "Comprehensive" - a good timeline is Comprehensively realistic, covering Scope, Budget, Risk, and Benefits (SBRB). If any one factor is ignored, the timeline is incomplete.

Topics

#implementation timelines#project planning#risk and scope management#realistic scheduling