nerdexam
Cisco

840-423 · Question #20

840-423 Question #20: Real Exam Question with Answer & Explanation

The correct answer is C. The timing should be realistic, given the scope, budget, risk, and potential benefits.. See the full explanation below for the reasoning.

Question

Which statement about implementation timelines is true?

Options

  • AThey should allow for the shortest total project elapsed time, regardless of risk.
  • BThey should have a good balance across a variety of business groups.
  • CThe timing should be realistic, given the scope, budget, risk, and potential benefits.
  • DThe duration should be set by a single executive sponsor so that accountability is easiest to

Community Discussion

No community discussion yet for this question.

Full 840-423 Practice