Microsoft
70-178 · Question #36
You need to view the following information for your project: - Current cost - Baseline cost - Actual cost - Remaining cost - Percentage of completion Which component will display the information?
The correct answer is C. The Project Statistics window. See the full explanation below for the reasoning.
Question
You need to view the following information for your project:
- Current cost
- Baseline cost
- Actual cost
- Remaining cost
- Percentage of completion
Which component will display the information?
Options
- AThe default Resource Sheet
- BThe default Task Sheet
- CThe Project Statistics window
- DThe default Cost Table
How the community answered
(62 responses)- A5% (3)
- B13% (8)
- C74% (46)
- D8% (5)
Community Discussion
No community discussion yet for this question.