nerdexam
Microsoft

70-178 · Question #35

70-178 Question #35: Real Exam Question with Answer & Explanation

Sign in or unlock 70-178 to reveal the answer and full explanation for question #35. The question stem and answer options stay visible for context.

Question

Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time. You need to ensure that the change in John's working time is reflected in the project schedule. What should you do?

Options

  • AUpdate the resource calendar for John by making Thursday as a non-working day and Saturday
  • BIn the Resource Information window for John, select the inactive option for Thursday and cancel
  • CUpdate the project calendar for John by making Thursday as a non-working day and Saturday as
  • DIn the Resource Information window for John, change John's availability by modifying the

Unlock 70-178 to see the answer

You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 70-178 Practice