nerdexam
Microsoft

70-178 · Question #35

Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on…

The correct answer is A. Update the resource calendar for John by making Thursday as a non-working day and Saturday. See the full explanation below for the reasoning.

Question

Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time. You need to ensure that the change in John’s working time is reflected in the project schedule. What should you do?

Options

  • AUpdate the resource calendar for John by making Thursday as a non-working day and Saturday
  • BIn the Resource Information window for John, select the inactive option for Thursday and cancel
  • CUpdate the project calendar for John by making Thursday as a non-working day and Saturday as
  • DIn the Resource Information window for John, change John's availability by modifying the

How the community answered

(44 responses)
  • A
    82% (36)
  • B
    2% (1)
  • C
    5% (2)
  • D
    11% (5)

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice