70-178 · Question #33

Your customer wants to receive your project's Timeline view in a document by e-mail. You need to create a document that contains only the Timeline view. You select the Timeline view. What should you…

The correct answer is D. Select Visual Reports. See the full explanation below for the reasoning.

Question

Your customer wants to receive your project's Timeline view in a document by e-mail. You need to create a document that contains only the Timeline view. You select the Timeline view. What should you do next?

Options

  • ASelect Sync With Task List.
  • BSelect Create PDF/XPS Document.
  • CSelect Save View.
  • DSelect Visual Reports.

How the community answered

(53 responses)
  • A
    13% (7)
  • B
    9% (5)
  • C
    4% (2)
  • D
    74% (39)