Question
You need to replace the resource assignment for an in-progress task. You also need to retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should you do?
Options
- AUse the Resource Name column drop-down list.
- BUse the Resource Pool feature.
- CUse the Team Planner feature.
- DUse the Level Selected feature.