nerdexam
Microsoft

70-178 · Question #32

You need to replace the resource assignment for an in-progress task. You also need to retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should you do?

The correct answer is C. Use the Team Planner feature. See the full explanation below for the reasoning.

Question

You need to replace the resource assignment for an in-progress task. You also need to retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should you do?

Options

  • AUse the Resource Name column drop-down list.
  • BUse the Resource Pool feature.
  • CUse the Team Planner feature.
  • DUse the Level Selected feature.

How the community answered

(55 responses)
  • A
    15% (8)
  • B
    5% (3)
  • C
    73% (40)
  • D
    7% (4)

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice