An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what…

The correct answer is A. Accept the risk. See the full explanation below for the reasoning.

Program Risk Management

Question

An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what appeared to be a significant risk resulted in a negligible risk. What should the program manager recommend to stakeholders for future similar situations?

Options

  • AAccept the risk
  • BSeek an expert opinion
  • CEstablish an on-call risk response team
  • DReview the risk severity matrix

How the community answered

(61 responses)
  • A
    70% (43)
  • B
    5% (3)
  • C
    8% (5)
  • D
    16% (10)

Topics

#risk acceptance#risk response strategy#geopolitical risk#risk severity