nerdexam
BICSI

RCDDV15 · Question #171

A program sponsor is concerned about the status of high-priority risks and budget variances. The program manager should refer to which of the following?

The correct answer is C. Program performance report. See the full explanation below for the reasoning.

Program Performance Management

Question

A program sponsor is concerned about the status of high-priority risks and budget variances. The program manager should refer to which of the following?

Options

  • AProgram status dashboard
  • BProgram management plan
  • CProgram performance report
  • DProgram management information system (PMIS)

How the community answered

(53 responses)
  • A
    15% (8)
  • B
    4% (2)
  • C
    72% (38)
  • D
    9% (5)

Topics

#program performance report#risk reporting#budget variance#program monitoring

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice