RCDDV15 · Question #168

A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues. What tool should be used to trigger a planned response…

See the full explanation below for the reasoning.

Program Performance Management

Question

A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues. What tool should be used to trigger a planned response when receiving lower than expected results?

Options

  • AKey performance indicators
  • BBenefits management plan
  • CCommunications management plan
  • DIshikawa diagram

Topics

#key performance indicators#performance monitoring#risk response triggers#program execution