A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues. What tool should be used to trigger a planned response when receiving lower than expected results?
Options
- AKey performance indicators
- BBenefits management plan
- CCommunications management plan
- DIshikawa diagram
Topics
#key performance indicators#performance monitoring#risk response triggers#program execution