BICSI
RCDDV15 · Question #172
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the…
The correct answer is C. Examine performance reports, audits, and inspections. See the full explanation below for the reasoning.
Program Procurement Management
Question
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk. What should the program manager do to monitor and control the supplier?
Options
- AUse expert judgment and update the program procurement plan
- BSeek stakeholder approval of program procurement management activities
- CExamine performance reports, audits, and inspections
- DReview proposal evaluation criteria, risk analyses, and mitigation strategies
How the community answered
(26 responses)- A12% (3)
- B4% (1)
- C77% (20)
- D8% (2)
Topics
#procurement management#supplier monitoring#performance audits#program execution
Community Discussion
No community discussion yet for this question.