A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million. Since the shutdown was not anticipated, what should the…
Sign in or unlock RCDDV15 to reveal the answer and full explanation for question #179. The question stem and answer options stay visible for context.
Program Risk Management
Question
A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million. Since the shutdown was not anticipated, what should the program manager do first?
Options
- AImplement the appropriate risk response plan and inform the stakeholders of the planned actions
- BUtilize contingency reserves to hire contractors, which will accelerate the schedule to meet the
- CEvaluate the impact, reassess the program risks, and determine options to be presented to the
- DCollaborate with the sponsor to determine options and negotiate a new date for the milestone
Unlock RCDDV15 to see the answer
You've previewed enough free RCDDV15 questions. Unlock RCDDV15 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#risk reassessment#issue management#milestone management#crisis response