Question

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million. Since the shutdown was not anticipated, what should the program manager do first?

Options

  • AImplement the appropriate risk response plan and inform the stakeholders of the planned actions
  • BUtilize contingency reserves to hire contractors, which will accelerate the schedule to meet the
  • CEvaluate the impact, reassess the program risks, and determine options to be presented to the
  • DCollaborate with the sponsor to determine options and negotiate a new date for the milestone