RCDDV15 · Question #179

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million. Since the shutdown was not anticipated, what should the…

The correct answer is C. Evaluate the impact, reassess the program risks, and determine options to be presented to the. See the full explanation below for the reasoning.

Program Risk Management

Question

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million. Since the shutdown was not anticipated, what should the program manager do first?

Options

  • AImplement the appropriate risk response plan and inform the stakeholders of the planned actions
  • BUtilize contingency reserves to hire contractors, which will accelerate the schedule to meet the
  • CEvaluate the impact, reassess the program risks, and determine options to be presented to the
  • DCollaborate with the sponsor to determine options and negotiate a new date for the milestone

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    17% (4)
  • C
    70% (16)
  • D
    9% (2)

Topics

#risk reassessment#issue management#milestone management#crisis response