A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity'?
The correct answer is A. Program risk register. See the full explanation below for the reasoning.
Program Risk Management
Question
A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity'?
Options
- AProgram risk register
- BProgram scope management plan
- CProgram risk management plan
- DComponent project risk registers
How the community answered
(57 responses)- A74% (42)
- B9% (5)
- C14% (8)
- D4% (2)
Topics
#opportunity management#risk register#program monitoring#risk identification