nerdexam
BICSI

RCDDV15 · Question #166

A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity'?

The correct answer is A. Program risk register. See the full explanation below for the reasoning.

Program Risk Management

Question

A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity'?

Options

  • AProgram risk register
  • BProgram scope management plan
  • CProgram risk management plan
  • DComponent project risk registers

How the community answered

(57 responses)
  • A
    74% (42)
  • B
    9% (5)
  • C
    14% (8)
  • D
    4% (2)

Topics

#opportunity management#risk register#program monitoring#risk identification

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice