A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor-related risk to the program…

The correct answer is B. Communicate the risk to all project managers to manage at the component level. See the full explanation below for the reasoning.

Program Risk Management

Question

A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of Impact and probability of occurring. What should the program manager do first?

Options

  • AObtain a risk reserve from the executive sponsor and execute a contingency plan
  • BCommunicate the risk to all project managers to manage at the component level
  • CAdd the risk details and analysis to the program risk register
  • DBrainstorm with the project manager to develop an appropriate risk response.

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    84% (26)
  • C
    10% (3)
  • D
    3% (1)

Topics

#risk escalation#risk management#program governance#component-level risk