The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization. What should the…

The correct answer is D. Document the risk and create a mitigation plan. See the full explanation below for the reasoning.

Program Risk Management

Question

The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization. What should the program manager do next?

Options

  • AUpdate the program benefits management plan and risk register
  • BImplement the mitigation plan for the identified risk
  • CAdjust the program scope to avoid the risk
  • DDocument the risk and create a mitigation plan

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    12% (3)
  • C
    4% (1)
  • D
    77% (20)

Topics

#risk identification#risk register#benefits realization#program schedule