RCDDV15 · Question #302
The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization. What should the…
The correct answer is D. Document the risk and create a mitigation plan. See the full explanation below for the reasoning.
Program Risk Management
Question
The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization. What should the program manager do next?
Options
- AUpdate the program benefits management plan and risk register
- BImplement the mitigation plan for the identified risk
- CAdjust the program scope to avoid the risk
- DDocument the risk and create a mitigation plan
How the community answered
(26 responses)- A8% (2)
- B12% (3)
- C4% (1)
- D77% (20)
Topics
#risk identification#risk register#benefits realization#program schedule