BICSI
RCDDV15 · Question #301
During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects. What should the program…
The correct answer is B. Review and update the stakeholder engagement plan. See the full explanation below for the reasoning.
Program Stakeholder Engagement
Question
During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects. What should the program manager do to address the situation'?
Options
- AReview and update the detailed stakeholder list
- BReview and update the stakeholder engagement plan
- CExecute the component project's communications management plan
- DUpdate the risk register.
How the community answered
(47 responses)- A4% (2)
- B79% (37)
- C6% (3)
- D11% (5)
Topics
#stakeholder engagement plan#communications management#program execution#stakeholder identification
Community Discussion
No community discussion yet for this question.