RCDDV15 · Question #203

A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement. What…

The correct answer is C. Meet with the program sponsor to address the issue. See the full explanation below for the reasoning.

Program Stakeholder Engagement

Question

A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement. What should the program manager do first?

Options

  • AMeet with the program management office to update the benefits management plan
  • BMeet with the organization's strategic planning committee to obtain clarification
  • CMeet with the program sponsor to address the issue
  • DMeet with the customer to determine if the stakeholder's requirement is valid

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    79% (22)
  • D
    7% (2)

Topics

#stakeholder conflict#strategic alignment#escalation#sponsor engagement