Question

A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement. What should the program manager do first?

Options

  • AMeet with the program management office to update the benefits management plan
  • BMeet with the organization's strategic planning committee to obtain clarification
  • CMeet with the program sponsor to address the issue
  • DMeet with the customer to determine if the stakeholder's requirement is valid