RCDDV15 · Question #204

A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

The correct answer is C. Assess all contracts to ensure all agreed conditions are mot. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

Options

  • ACertify contract completion
  • BConduct a procurement audit to review the procurement process
  • CAssess all contracts to ensure all agreed conditions are mot
  • DReview contract management plan for completeness

How the community answered

(56 responses)
  • A
    4% (2)
  • B
    7% (4)
  • C
    73% (41)
  • D
    16% (9)

Topics

#contract closure#procurement audit#program closeout#contract conditions