When should a program manager approve the closure of a component project?
The correct answer is A. When acceptance criteria of the project are met. See the full explanation below for the reasoning.
Program Life Cycle Management
Question
When should a program manager approve the closure of a component project?
Options
- AWhen acceptance criteria of the project are met
- BWhen the project has delivered the protect benefits
- CWhen program deliverables are complete
- DWhen project deliverables are complete
How the community answered
(35 responses)- A71% (25)
- B3% (1)
- C14% (5)
- D11% (4)
Topics
#component project closure#acceptance criteria#program governance#deliverable approval