When should a program manager approve the closure of a component project?

The correct answer is A. When acceptance criteria of the project are met. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

When should a program manager approve the closure of a component project?

Options

  • AWhen acceptance criteria of the project are met
  • BWhen the project has delivered the protect benefits
  • CWhen program deliverables are complete
  • DWhen project deliverables are complete

How the community answered

(35 responses)
  • A
    71% (25)
  • B
    3% (1)
  • C
    14% (5)
  • D
    11% (4)