A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the…

The correct answer is D. Add the lack of skilled resources to facilitate the large number of change requests to the issue log. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks. What should the program manager do next to address this risk?

Options

  • APrioritize which resources are critical to the project based on an impact analysis of the critical
  • BPrioritize which change requests are critical to the project based on an impact analysis, resource
  • CMandate that no component project change requests will be processed until overdue milestones
  • DAdd the lack of skilled resources to facilitate the large number of change requests to the issue log

How the community answered

(43 responses)
  • A
    9% (4)
  • B
    2% (1)
  • C
    7% (3)
  • D
    81% (35)