A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the…

Sign in or unlock RCDDV15 to reveal the answer and full explanation for question #239. The question stem and answer options stay visible for context.

Program Life Cycle Management

Question

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks. What should the program manager do next to address this risk?

Options

  • APrioritize which resources are critical to the project based on an impact analysis of the critical
  • BPrioritize which change requests are critical to the project based on an impact analysis, resource
  • CMandate that no component project change requests will be processed until overdue milestones
  • DAdd the lack of skilled resources to facilitate the large number of change requests to the issue log

Unlock RCDDV15 to see the answer

You've previewed enough free RCDDV15 questions. Unlock RCDDV15 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#change requests#resource constraints#issue log#milestone management