BICSI
RCDDV15 · Question #149
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program…
The correct answer is D. Feedback and lessons learned. See the full explanation below for the reasoning.
Program Life Cycle Management
Question
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations. At this stage, what is expected during the post-review session organized by the program manager?
Options
- AEarned value (EV) report
- BCustomer sign-off
- CBenefits register updates
- DFeedback and lessons learned
How the community answered
(21 responses)- A5% (1)
- B5% (1)
- C10% (2)
- D81% (17)
Topics
#program closure#lessons learned#benefits realization#post-review session
Community Discussion
No community discussion yet for this question.