nerdexam
BICSI

RCDDV15 · Question #229

RCDDV15 Question #229: Real Exam Question with Answer & Explanation

The correct answer is C. The schedule is US$10.000 over budget. See the full explanation below for the reasoning.

Question

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of USS2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000. Based on this information, the program manager determines which of the following?

Options

  • AThe schedule is US%30.000 under budget
  • BThe cost is US$20.0O0 under budget
  • CThe schedule is US$10.000 over budget
  • DThe cost is USS20.000 over budget

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice