Question
A program manager assigns project managers to five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?
Options
- ARotate the responsibility for risk assessment among the program components
- BCoach the project managers to manage project resources
- CCross-train the project managers to share expertise
- DPrepare the project managers to assume larger roles with more responsibility.