A program manager assigns project managers to five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?

The correct answer is B. Coach the project managers to manage project resources. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A program manager assigns project managers to five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?

Options

  • ARotate the responsibility for risk assessment among the program components
  • BCoach the project managers to manage project resources
  • CCross-train the project managers to share expertise
  • DPrepare the project managers to assume larger roles with more responsibility.

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    72% (18)
  • C
    16% (4)
  • D
    8% (2)

Topics

#team development#coaching#project manager development#resource management