The correct answer is B. Coach the project managers to manage project resources. See the full explanation below for the reasoning.

Question

A program manager assigns project managers to five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?

Options

  • ARotate the responsibility for risk assessment among the program components
  • BCoach the project managers to manage project resources
  • CCross-train the project managers to share expertise
  • DPrepare the project managers to assume larger roles with more responsibility.