RCDDV15 · Question #237

A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest. What action should the program manager take…

The correct answer is A. Rework the stakeholder engagement plan to foster better relationships with the affected. See the full explanation below for the reasoning.

Program Stakeholder Engagement

Question

A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest. What action should the program manager take first?

Options

  • ARework the stakeholder engagement plan to foster better relationships with the affected
  • BReview the stakeholder register to determine the ability of the affected stakeholder group(s) to
  • CAssess the risk of sustained negative media coverage
  • DDiscuss the issues with the governance board to determine next steps

How the community answered

(36 responses)
  • A
    81% (29)
  • B
    11% (4)
  • C
    3% (1)
  • D
    6% (2)

Topics

#stakeholder engagement plan#public relations#negative stakeholder#communications management