Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance. To resolve this situation, which of the…

The correct answer is B. Stakeholder communications requirements. See the full explanation below for the reasoning.

Program Stakeholder Engagement

Question

Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance. To resolve this situation, which of the following must go through critical review and change?

Options

  • AProgram Benefits Management domain
  • BStakeholder communications requirements
  • CProgram communications report
  • DProgram communications management plan

How the community answered

(35 responses)
  • A
    11% (4)
  • B
    83% (29)
  • C
    3% (1)
  • D
    3% (1)

Topics

#communications management plan#stakeholder communications#ad-hoc requests#reporting duplication