A program has been established and preparation is complete. Component projects are planned as a part of which of the following?

The correct answer is D. Program delivery phase. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A program has been established and preparation is complete. Component projects are planned as a part of which of the following?

Options

  • AProgram definition phase
  • BProgram formulation
  • CProgram planning
  • DProgram delivery phase

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    8% (2)
  • D
    77% (20)