RCDDV15 · Question #90

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited…

The correct answer is D. Conduct a stakeholder meeting to allow everyone to state their priorities. See the full explanation below for the reasoning.

Program Stakeholder Engagement

Question

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits. Which of the following actions should the program manager take?

Options

  • AFocus on the internal stakeholders to ensure cost and) schedule objectives are achieved
  • BBalance stakeholder needs through the use of trade-offs among the stakeholder groups
  • CFocus on the external stakeholders to ensure the intended benefits are achieved
  • DConduct a stakeholder meeting to allow everyone to state their priorities

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    10% (3)
  • C
    3% (1)
  • D
    83% (24)

Topics

#stakeholder conflict#cost-schedule-benefits tradeoffs#stakeholder engagement#program balance