A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?

The correct answer is A. Request permission from the program governance board to initiate program closure activities. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?

Options

  • ARequest permission from the program governance board to initiate program closure activities
  • BPresent additional opportunities to the program sponsor
  • CApply the remaining budget to operational activities
  • DApply the remaining budget to deferred enhancement requests

How the community answered

(30 responses)
  • A
    73% (22)
  • B
    3% (1)
  • C
    7% (2)
  • D
    17% (5)

Topics

#program closure#governance board approval#budget management#closure activities

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice