RCDDV15 · Question #91

A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?

Sign in or unlock RCDDV15 to reveal the answer and full explanation for question #91. The question stem and answer options stay visible for context.

Program Life Cycle Management

Question

A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?

Options

  • ARequest permission from the program governance board to initiate program closure activities
  • BPresent additional opportunities to the program sponsor
  • CApply the remaining budget to operational activities
  • DApply the remaining budget to deferred enhancement requests

Unlock RCDDV15 to see the answer

You've previewed enough free RCDDV15 questions. Unlock RCDDV15 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#program closure#governance board approval#budget management#closure activities