nerdexam
BICSI

RCDDV15 · Question #92

RCDDV15 Question #92: Real Exam Question with Answer & Explanation

The correct answer is D. Submit a change request to extend the program schedule. See the full explanation below for the reasoning.

Question

A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the protects several mandatory changes are identified that would extend the program's completion date. What is the next step for the program manager?

Options

  • AApply resource leveling to ensure the program is completed on schedule
  • BUpdate the schedule to reflect the extended completion date
  • CAdjust working hours to ensure the program is completed on schedule
  • DSubmit a change request to extend the program schedule

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice