RCDDV15 · Question #108
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set, if the tolerance range is too narrow on a…
The correct answer is D. Slow down in program implementation. See the full explanation below for the reasoning.
Program Governance
Question
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?
Options
- AReduction in program quality
- BDegradation of program communications
- CReduction in program risk
- DSlow down in program implementation
How the community answered
(48 responses)- A10% (5)
- B6% (3)
- C2% (1)
- D81% (39)
Topics
#change control#tolerance range#scope management#program implementation