A program manager has four projects pending approval Senior management asks the program manager to identity a project for potential elimination based on the return on investment. The program manager…

The correct answer is D. Project D. See the full explanation below for the reasoning.

Program Governance

Question

A program manager has four projects pending approval Senior management asks the program manager to identity a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision. Which project should the program manager select to be cancelled?

Exhibit

RCDDV15 question #189 exhibit

Options

  • AProject A
  • BProject B
  • CProject C
  • DProject D

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    10% (3)
  • C
    7% (2)
  • D
    80% (24)

Topics

#return on investment#project elimination#portfolio prioritization#financial analysis