The program manager of a multinational program must reconcile data including subject matter experts* labor hour estimates and other direct resource hour estimates. In addition the program manager…

The correct answer is A. Currency exchange rates. See the full explanation below for the reasoning.

Program Financial Management

Question

The program manager of a multinational program must reconcile data including subject matter experts* labor hour estimates and other direct resource hour estimates. In addition the program manager must prepare the cash flow analysis Which of the following should be considered to get a baseline budget?

Options

  • ACurrency exchange rates
  • BComponent cost estimates
  • CBaseline schedule
  • DProgram payment schedules

How the community answered

(24 responses)
  • A
    75% (18)
  • B
    4% (1)
  • C
    13% (3)
  • D
    8% (2)

Topics

#currency exchange rates#baseline budget#multinational program#cash flow analysis