RCDDV15 · Question #210

The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee…

The correct answer is D. Project A is running behind schedule and is over budget projects B, C, and D are on schedule. See the full explanation below for the reasoning.

Program Financial Management

Question

The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee. What do the current findings show?

Exhibit

RCDDV15 question #210 exhibit

Options

  • AProject C is running behind schedule and is over budget, projects A, B and D are on schedule
  • BProject A is running ahead of schedule and is under budget projects B, C and D are behind
  • CThe overall program is performing within an acceptable level of variance
  • DProject A is running behind schedule and is over budget projects B, C, and D are on schedule

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    10% (5)
  • D
    84% (41)

Topics

#earned value management#cost variance#schedule variance#performance reporting