The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee…
The correct answer is D. Project A is running behind schedule and is over budget projects B, C, and D are on schedule. See the full explanation below for the reasoning.
Program Financial Management
Question
The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee. What do the current findings show?
Exhibit
Options
- AProject C is running behind schedule and is over budget, projects A, B and D are on schedule
- BProject A is running ahead of schedule and is under budget projects B, C and D are behind
- CThe overall program is performing within an acceptable level of variance
- DProject A is running behind schedule and is over budget projects B, C, and D are on schedule
How the community answered
(49 responses)- A2% (1)
- B4% (2)
- C10% (5)
- D84% (41)
Topics
#earned value management#cost variance#schedule variance#performance reporting